We are making some good headway on the Arapahoe Sports remodel. The excavation work is substantially done. The footers are poured. The foundation walls are poured. The electrical conduits are installed. The slab is poured. I think we will be seeing framed walls going up soon.

We have made similar progress on the deck, walkway, ramp and plaza remodel. A fair bit more excavation work to go. The footers are poured and the concrete forms are being prepared for the foundation wall pours.



2 comments:

Brownjuan Brown said...

The floorspace that the old Arapahoe Sports occupied: will that be added to indoor cafeteria seating or is it being absorbed into the total space for the new Arapahoe Sports?

As always, thanks for your posted information about all thing "A-Basin".....

Alan Henceroth - COO said...

The floor space that was old Arapahoe Sports will also be in the new Arapahoe Sports. Of note, there will be approximately 100 additional outdoor seats for eating as we re-do the deck and plaza.