Pallavicini Motor Room

The Pali motor room was set on Friday. The cables (or wire ropes) for both Molly Hogan and Pallavicini arrived Thursday. 10 of 12 Pali tower holes have been dug. The lift team will spend the next several days working on the remaining 2 tower holes and setting all the concrete forms. Perhaps as soon as the end of the week, we will have another big helicopter day flying concrete.