Thursday, August 23, 2018

Beavers' Towers

The first truckload of Beavers Chairlift towers showed up today. The Leitner Poma crew will be installing the tower head and sheave assemblies. The next step is to fly concrete for the tower foundations. As soon as we can pry a helicopter from the fires out West, we will be doing that (probably in 1-2 weeks). Once the concrete is set, the towers will be set in place.