Even with all the excitement of opening tomorrow, we are still working hard at getting the Beavers Chairlift finished. The wire rope will be installed over the next couple of days and the rope splice will occur early next week. Soon after the splice, the carriers (the chairs) will be attached to the line. Throughout all of this, there is a lot of work being done by the electricians. We anticipate the Acceptance Test (Load Test) to be completed the first week of November. That gives us plenty of time for a Beavers Chairlift December opening.
See you skiing in the morning.