Monday, October 10, 2022

Crane Is Off The Top

Building Lenawee Express, there are a few things that really make me sweat. To start, building the lift is a 6 month project and the road to the Summit is only open about 3 1/2 months. It doesn't take much snow and wind to make the last 1/2 mile impassible. So, getting all the lift equipment and heavy machinery to The Basin, to The Summit and fully assembled were some nerve racking tasks. I am very relieved to say all the big work is done and the crane came down the hill. Obviously, there is a lot more to do, but the Summit construction activities that would be thwarted by heavy snowfall are complete. Whew!